View Issue Details

This issue affects 1 person(s).
 2
IDProjectCategoryView StatusLast Update
07320Bug reportsImport/Exportpublic2013-02-22 21:32
Reporterrgrela Assigned Toc_schmitz  
PrioritynormalSeverityminor 
Status closedResolutionno change required 
Product Version2.00+ 
Fixed in Version2.00+ 
Summary07320: Problems with the "completed" date in responses of surveys
Description

We have problems with the "completed" date in responses of surveys that we had created in old version limesurvey, 1.92. The date saved in the version 2.00 is allways 1980-01-01

We think that this happen when the survey no have check "Date Stamp" in General Settings- Notification & Data Management.

"Completed" Date is correct in version 2.00 if "Date Stamp" is checked.
"Completed" Date is correct in version 1.92 if "Date Stamp" is checked.
"Completed" Date is correct in version 1.92 if "Date Stamp" is no checked.
"Completed" Date is NOT correct in version 2.00 if "Date Stamp" is no checked.

is it possible? is it a bug? is it a new behavior in the new version?

TagsNo tags attached.
Attached Files
completeddate.GIF (26,069 bytes)   
completeddate.GIF (26,069 bytes)   
Bug heat2
Complete LimeSurvey version number (& build)130129
I will donate to the project if issue is resolvedNo
BrowserIE, Firefox
Database type & versionMysql
Server OS (if known)Linux
Webserver software & version (if known)Apache
PHP Version5.2

Users monitoring this issue

There are no users monitoring this issue.

Activities

c_schmitz

c_schmitz

2013-02-22 21:32

administrator   ~24199

Yes, the behaviour was changed - this is correct.

Issue History

Date Modified Username Field Change
2013-02-22 15:23 rgrela New Issue
2013-02-22 15:23 rgrela File Added: completeddate.GIF
2013-02-22 21:32 c_schmitz Note Added: 24199
2013-02-22 21:32 c_schmitz Status new => closed
2013-02-22 21:32 c_schmitz Assigned To => c_schmitz
2013-02-22 21:32 c_schmitz Resolution open => no change required
2013-02-22 21:32 c_schmitz Fixed in Version => 2.00+